New buildings SANA Sportpark
At the end of 2008, the city of Offenbach decided to develop the Tambour site into a modern sports center. OPG took over the project management for the new construction of the SANA sports park.
The premises include three clubhouses, changing rooms and a warehouse. The OFC youth team and the SG Wiking and FC Bieber clubs moved into their new home here in November 2010. The club building and the two-storey changing room building were built in solid construction in accordance with the latest energy standards at the time. The storage building is a large hall in steel construction.
The athletics facility on site was completed by mid-2012. It completes the expansion of the SANA Sportpark into the largest grassroots sports center in the city of Offenbach. Soccer and athletics, recreational and professional athletes and schoolchildren will now find their place and optimal conditions to practice their sports here.
Facts about the project:
- Club building with three clubhouses in solid construction (single-storey)
- Current energy standards with a local heating connection via the heating system of the changing room building
- Gross floor area (GFA) of 330 m²
- Storage building + hall in steel construction with a gross floor area of around 270 m²
- Changing room building in solid construction with two storeys according to current energy standards with an air-heat pump (heating and hot water preparation) to reduce operating costs
- Changing room area with around 960 m² GFA (groundsman's room, first-aid room, public toilets, 12 team changing rooms with shower rooms, eight referees' and coaches' changing rooms)